Intel is pushing back the completion date of its $28 billion semiconductor project in New Albany, Ohio. The company now ...
Intel’s plans to build two chip factories in New Albany, Ohio for an investment of more than $28 billion have been postponed.
The first phase of the facility, known as Mod 1, should be finished in 2030, with chip production beginning between 2030 and ...
The site in New Albany, Ohio, is now set to be completed in 2030, with operations starting as late as 2031, compared with the ...
There is still hope the project will happen as Intel promises, but if the plan falls through, the state must claw back as much as possible.
COLUMBUS, Ohio -- Intel’s massive semiconductor project in central Ohio has been delayed, again. On Friday, the company ...
Intel's Ohio facility, initially slated for completion in 2025, is now set to be finished in 2030, with operations starting ...
Intel’s massive computer chip factory, originally scheduled to open this year, has been delayed again, this time to the next ...
Intel's promised $28 billion chip fabrication plants in Ohio are facing further delays, with the first factory in New Albany ...
The chip maker is delaying the construction of a $28 billion semiconductor factory project in Ohio by about five years.
Intel says it won't complete construction on one of two New Albany fabs for another five years, citing its business needs and ...
Intel Corp. has once again pushed back the expected opening for its semiconductor project in central Ohio.